Transneft to start external power supply facilities construction for “Kuyumba-Taishet” in 2015
Edited by Rhod Mackenzie / 2014-04-02 05:53:00
Transneft maps out to start the construction of external power supply facilities for the main oil pipeline Kuyumba-Taishet at the beginning of 2015. The press-service of the “PMO ESPO” LLC stated.
According to the statement, the launch of the double-circuit transmission line110 kW of 326 km length and 3 substations of a total production capacity of 42 MVA is planned for Q3-4, 2016, a representative of the press-service said to ITAR-TASS. They are about to finish design and survey work and get the positive conclusion of a state appraisal on external power supply facilities construction project by December 2014 in the company.