Cub-Gaz restarts drilling in Eastern Ukraine
Cub-Gaz of the businessman Y. Kulchik restarts drilling at the well Makeyevskaya-22 in the Lugansk region in Eastern Ukraine, due to improving of the safety situation nearby the Makeyevskoye, Olgovskoye and Northern- Makeyevskoye deposits.
The main target in the drilling of М-22 is zone S6 that appeared to be very productive at wells М-16, М-17, and O-15. They also have the secondary targets in zones S5 and S7. The total time needed for drilling, testing and completion of the work is 80 days.
In the case of successful drilling, the well will be adjusted quickly because the company has built all the necessary pipelines awaiting for the drilling this year.