Chernomortransneft to construct a new oil pipeline Tikhoretsk-Novorossiysk -3 by August 2017
In the framework of realization of the “South” project, Chernomortransneft has started the development of the underwater line via the Chelbas river of a route oil pipeline Tikhoretsk-Novorossiysk -3.
The trench digging method has been selected.
The trench has been installed in full volume.
The Lupingi route oil pipeline Tikhoretsk-Novorossiysk -2 will be connected into a single branch from the transshipment base Tikhoretskaya to the Grushovaya site of the Sheskharis transshipment complex, e.g. a new route oil pipeline Tikhoretsk-Novorossiysk -3 will be formed which is meant for oil pumping.
New sites of the 89.6 km long Du700 oil pipeline are being constructed now.
The total length of the route oil pipeline Tikhoretsk-Novorossiysk -3 will be 244 km.
It is planned to construct the oil pumping station #5 with the accompanying subsystems at the transshipment base Tikhoretskaya and steel vertical reservoirs with the volume of 10 thousand cubic m at the oil pumping station #4 Crimea.