Final joint has been welded at Suzun-Vankor oil pipeline

​RN-Vankor completes the construction of the linear part of the interfield oil pipeline Suzun-Vankor – the final joint of the pipeline has been welded. The construction works have been held since December 2014.

The length of the pipeline which connected the Suzun and Vankor deposits is 99 km, pipe diameter – 530 mm. aiming for the minimization of the influence on the frozen soil, reliability and stability of the oil pipeline, the thermal stabilization technology is applied.

All requirements of environmental protection have been met at the construction. The works were held in winter.

The launch of the interfield oil pipeline Suzun- Vankor is accompanies with the launch of other objects of the first complex of the Suzun deposit – clusters of oil wells, oil preparation unit, and other objects of production and auxiliary meaning.

Full text available to premium subscribers only.

Buy full access for 24 hours now

or

Request a quote to subscribe for a longer period

Oil and Gas, Metals and Mining, News from Russia and neighbouring countries
12 Northfields Prospect; London, - SW18 1PE; United Kingdom
E 51° 27.454518" S 0° 14.101236"

Theme by Danetsoft and Danang Probo Sayekti inspired by Maksimer