Half of pipes necessary for Power of Siberia have been delivered to Yakutia
Edited by Rhod Mackenzie / 2015-08-11 02:07:49
CNPC Oil and Gas Russia China Oil and Gas Magnitogorsk metallurgic plant MMK Novolipetsk Steel NLMK Severstal TMK Pipes Power of Siberia (Sila Sibiri) United Metallurgical Company (OMK) Russia Metals and Mining Russia Oil and Gas Gas Gazprom Steel Pipelines
Over 200 thousand tons of pipes have been delivered to Yakutia for the construction of Power of Siberia. This is a half of the necessary volume.
Currently 216 thousand tons of pipes have been shipped, this is 49% of the total volume (plan – 439 thousand tons). This winter over 185 thousand pipes will be welded in the Olekminsky district.
The total volume of cargo which will be delivered in the navigation period for the construction of Power of Siberia is 800 thousand tons. The navigation will be over in late September-October.
The cargo shipment is held according to the schedule. The first shipment started in May.