In 2015 Chernomorneftegaz commissions 5 new wells.
Edited by Rhod Mackenzie / 2016-01-13 11:17:56
Within January-December 2015 natural gas production at SUE RC "Chernomorneftegaz" amounted to 1.844 billion cubic meters, which corresponds to the planned target (100.03% of the plan), the press service of the company reports.
Extraction of oil and gas condensate amounted to 61.1 thousand tons (102.4% of the plan).
5 new wells were commissioned. The program of repair and overhaul of existing wells was completed.