Norilsk Nickel promises to complete the first stage of reconstruction at Talnakh dressing plant by the end of the year
Norilsk Nickel prepares to launch the first stage of the Talnakh dressing plant (TOF), whose reconstruction is carried out under the company's new development strategy and aims to increase the capacity of the plant. The reconstruction project consists of two startup complexes, which include the installation of modern technological equipment, the extension of the main building of the plant, the construction of new facilities and a tailing dump.
The construction of the first startup complex started in the middle of last year. The launch is scheduled for the end of 2014. Now 36 rooms for flotation machines (volume of each room is 100 cubic meters) are installed. The aim of the first start-up complex launch is the decommissioning of 24 rooms of flotation machines,who have exhausted their resources.