Transneft-Ural carries out reconstruction of tank battery
Edited by Rhod Mackenzie / 2015-08-20 12:45:33
Transneft - Ural carries out planned work on updating the tank farms of the linear production-dispatching stations Nurlino, Cherkasy and Salavat , Khokhly and Kaltasy. Currently, construction and installation works are carried out at 18 tank batteries.
In accordance with the approved program of the technical re-equipment, the reconstruction and overhaul in 2015, the company planned to work on replacement of metal structures at 20 vertical steel tanks and vertical steel tanks with pontoons with total capacity of 270 thousand cubic meters and technical re-equipment of the reinforced concrete tank with capacity of 10 thousand cubic meters