Contracts for part of equipment for the Amur GPP are to be concluded before the end of 2015.
Edited by Rhod Mackenzie / 2015-09-28 06:16:40
Oil and Gas Refining Russia Petrochemicals PolymerUpdate Sibur Russia Oil and Gas Gas Gazprom Production and Refining
Contracts for the supply of long term manufactured equipment for the of Amur gas processing plant are expected to be concluded before the end of 2015, the general director of NIPIGas (a subsidiary of Sibur) Aleksey Vertyagin stated in an interview to "Alpha channel".
"Today the design is in progress, distributors are selected. Before the end of the year we plan to conclude contracts for the supply of equipment with long period of manufacturing and further continue training, including the construction of a shift camp for 5 thousand people", - A. Vertyagin stated.