Pre-commissioning has started at the construction site of the coal dust injection utility for West Siberian metal works of Evraz
Edited by Rhod Mackenzie / 2014-03-31 09:32:07
The pre-commissioning has started at the construction site of the coal dust injection utility for the West Siberian metal works (ZSMC) of Evraz. They have completed the main facilities of the complex for the coal dust injection utility, finished the assembling of equipment, the electric mechanical products and automated management systems. They completed preparing of ZSMC ‘s blast furnaces for the coal dust injection. They execute checking of the signals and individual testing of all coal dust injection equipment. After completion of this work, the specialists will start dry run of the major equipment and will start hot commissioning.